IREN Q1 FY2027 10-Q: $18.9B of Commitments vs $8.9B of Cash and Credit
Listen to this report
The Hook
The market's read on IREN $IREN this month is a timing story: AI Cloud revenue nearly tripled, the $4 billion run-rate target slipped from year-end to January or February, and $6 billion of this fiscal year's build is not yet financed. The 10-Q for the quarter ended September 30, 2026 puts a harder number under that. IREN had $18,947M of signed capital commitments at quarter-end, up from $13,810M in June, against $5,778M of cash and restricted cash and $3,157M of undrawn committed debt. That is $8,935M of funding in hand for $18.9 billion of signed purchases, before a dollar of the "targeted" money arrives.
And the money that built IREN so far is not the money that will finish it. Of its $10,041M of debt principal, $6,745M is convertible notes carrying effective rates of 0.37% to 4.22%. The four largest issues, $6,300M of them, convert at $51.40 to $85.63 a share. IREN closed at $11.82 on November 20 (stockanalysis.com), so those notes are now plain debt, and the two new GPU loans signed in August carry effective rates of 10.38% and 10.70%.
Company Snapshot
IREN Limited is a Sydney-headquartered operator that began as a Bitcoin miner and is converting its land, grid power and data centers in Canada, the United States and elsewhere into an AI cloud: GPU capacity sold by the hour (AI Cloud Services) and whole data halls leased to a customer (AI Cloud Lease, which began this quarter with Horizon 1). It files with the SEC as a domestic filer, with a June fiscal year. This brief reads the Form 10-Q for the first quarter of fiscal 2027, the three months ended September 30, 2026, filed November 5, 2026.
The Financial Story
The mix flipped in a year. Revenue was $228M, against $240M a year earlier, but almost none of it is the same business. AI Cloud revenue was $200M ($135M of services and $65M of lease revenue from Horizon 1), against $7M a year ago; Bitcoin mining fell to $28M from $233M. AI Cloud cost of revenue before depreciation was $28M, so the segment kept 86% of its revenue at that line. Below it, the company did not: SG&A was $217M, of which $106M was stock-based compensation, depreciation and amortization was $148M, and the operating loss was $186M. Net loss was $263M, or $0.66 a diluted share. (An Earnings Whispers review of the November 5 results put the loss at $0.62 a share; the 10-Q says $0.66.) Adjusted EBITDA, the company's own non-GAAP measure in the November 5 earnings release, was $66M.
Three customers are 70% of revenue. The revenue note names Customer A at 28%, Customer B at 24% and Customer C at 18%, all in AI Cloud. The fiscal 2026 10-K described "significant customer concentration" in its risk factors but gave no AI Cloud customer percentages; this is the first quarter the concentration is on a page with numbers on it. The 10-K's risk factors name the anchors: a five-year Microsoft agreement of about $9.7B of contract value and a five-year NVIDIA cloud contract of about $3.4B, together "a substantial majority of our contracted revenue."
| Quarter ended September 30 | 2026 | 2025 |
|---|---|---|
| AI Cloud revenue | $200M | $7M |
| Bitcoin mining revenue | $28M | $233M |
| Total revenue | $228M | $240M |
| SG&A (incl. stock comp) | $217M | $138M |
| Depreciation and amortization | $148M | $85M |
| Operating loss | $(186)M | $(76)M |
| Contractual interest on debt | $48M | $8M |
| Net income (loss) | $(263)M | $385M |
| Operating cash flow | $529M | $142M |
| Increase in deferred revenue | $645M | $22M |
| Cash paid for PP&E and computer hardware | $4,824M | $280M |
Operating cash flow was customer prepayments. The cash flow statement shows $529M from operations. But deferred revenue rose $645M in the quarter, money customers paid ahead of service, mostly against leases. Take that out and operations used $116M. Total deferred revenue is now $2,544M, of which $2,096M is prepaid lease revenue. That is real cash and a real sign of customer commitment, and it is also a liability that is earned back only as capacity is delivered on time, which is exactly what slipped this quarter.
The build is outrunning the balance sheet. IREN paid $2,693M for computer hardware and $2,131M for other property and equipment in one quarter, and owed another $2,493M of capital spending still sitting in payables at September 30. Cash and restricted cash fell to $5,778M from $7,620M even after $2,360M of new borrowing and $498M of share sales. Debt principal rose to $10,041M from $7,706M, and the current portion jumped to $950M from $169M because the new GPU loans amortize fast: GPU Financing 2.0 over 30 months from each draw, GPU Financing 3.0 in 36 monthly installments. Scheduled principal is $723M for the rest of fiscal 2027 and $1,059M in fiscal 2028.
| Funding at September 30, 2026 | Amount |
|---|---|
| Cash and cash equivalents | $3,522M |
| Restricted cash | $2,256M |
| Undrawn: GPU Financing 2.0 | $1,500M |
| Undrawn: DDTL Facility | $1,132M |
| Undrawn: USPP Senior Notes | $525M |
| Cash plus undrawn committed debt | $8,935M |
| Signed capital commitments | $18,947M |
The commitments note changed wording. The 10-K split June's $13,810M of commitments by timing: $13,611M payable within 12 months. The 10-Q drops the timing table and adds a sentence the 10-K did not have: "Certain of the Group's purchase commitments provide cancellation flexibility, subject to contractual terms that may include cancellation charges or reimbursement of supplier costs." Read plainly, the company is telling investors some of the $18.9B can be slowed or cut, at a cost. That is a lever, and it is also the first time the filing has needed to mention it.
Charged is not paid. Income tax was a $2M charge this quarter on a $261M pre-tax loss, from valuation allowances; cash paid for income taxes was zero. A year ago IREN was charged $191M, mostly deferred tax on an unrealized gain on financial instruments, and also paid nothing.
Capital returns: none, and the share count is up 50% in thirteen months. There were no buybacks and no dividends. IREN funds the build partly through its at-the-market program: 12.3M shares in the quarter, recorded at about $44 a share net of costs, plus 12.6M shares issued to buy Mirantis, a cloud software company, for $538M. After quarter-end it sold 17.4M more for about $630M, about $36 a share. The November 24 AGM asks shareholders to renew approval for share repurchases under the prepaid forward and capped call contracts tied to the 2029 and 2030 convertibles; that is the settlement mechanics of existing hedges, not a buyback program.
| Ordinary shares outstanding | Shares |
|---|---|
| June 30, 2025 | 257.2M |
| September 30, 2025 | 282.9M |
| June 30, 2026 | 380.2M |
| September 30, 2026 | 406.9M |
| October 30, 2026 (cover page) | 424.4M |
The ATM sales are the part of the story that has aged best: IREN sold 29.6M shares between July and early November at roughly $36 to $44, and they now trade at $11.82. The cheap equity window those sales used is shut at today's price.
Valuation - what it's worth as a normal business
Where it trades. At $11.82 (stockanalysis.com, close on November 20, 2026) and the 10-Q cover count of 424.4M shares, IREN's market value is about $5.02B, slightly below its $5,116M of book equity. Adding $10,041M of debt principal and $311M of finance leases and subtracting $5,778M of cash and restricted cash gives an enterprise value of about $9.59B. Against the FY2027 revenue consensus of $2.39B and the FY2028 consensus of $7.15B (stockanalysis.com, S&P Global data as of November 19), that is about 4.0x this year's sales and 1.3x next year's. The 20 analysts there rate it a Buy with an average target of $52.74; JPMorgan cut its target to $55 from $65 on November 9 (per Finviz, November 18). The stock fell about 18% on November 20 in a broad AI selloff with no company news (per MarketBeat, November 20). Some of the restricted cash is held for specific projects, so the true net debt is a little higher than the figure above.
Scenario DCF. IREN has no steady free cash flow yet, so this values a steady state about two and a half years out and discounts it back. "Owner cash flow" is EBITDA minus interest, cash tax and the spending to replace GPUs as they age, at roughly 30% of revenue. House defaults: 9% discount rate and 3% terminal growth.
| Scenario | Steady-state revenue | EBITDA margin | Interest | GPU reinvestment | Owner cash flow | Shares | Implied value a share |
|---|---|---|---|---|---|---|---|
| Bear: delays, more financing at 10%+ | $3.0B | 55% | $0.90B | $0.90B | $(0.15)B | 450M | about $0 |
| Base: the contracted $4B ARR, no expansion | $4.0B | 60% | $0.90B | $1.20B | $0.25B | 450M | about $8 |
| Bull: FY2028 consensus delivered | $7.0B | 65% | $1.20B | $2.10B | $1.10B | 500M | about $30 |
At $11.82 the market is pricing roughly $4.5B of steady-state revenue under the base cost structure: the contracted $4B ARR delivered, a little expansion, and no equity wipe from the funding gap. The bear row is not a forecast; it is what happens to the equity of a business carrying $10B of debt when its margin after reinvestment does not cover interest.
Peer re-rating. In late May, before the neocloud selloff, the Clouded Judgement newsletter (May 22, 2026) put CoreWeave near 6x next-twelve-months revenue and IREN and Nebius near 10x. Applied to the FY2027 revenue consensus of $2.39B, with net debt of $4,574M and 424.4M shares:
| EV / FY2027 revenue | Implied EV | Implied value a share |
|---|---|---|
| 4.0x (today) | $9.6B | $11.82 |
| 6x (CoreWeave, May) | $14.3B | about $23 |
| 10x (IREN's own May multiple) | $23.9B | about $46 |
Taken together, implied value runs from about $0 to about $30 a share on the DCF and $23 to $46 on peer multiples that no longer hold. That is implied value under stated assumptions, not a price target and not investment advice. The gap between the two methods is the funding question: peer multiples assume the money arrives, the DCF charges for it.
Risks
Delivery comes first: the $4B ARR date has already moved once, revenue is recognized only after commissioning and customer acceptance, and the prepaid leases are earned only on delivery. Funding comes second: $18.9B of commitments against $8.9B of cash and undrawn debt, a remaining $6B the company calls "subject to market conditions", and a share price that makes new equity expensive and new convertibles hard to price. The 10-Q's liquidity note still concludes that cash, operating cash flow and "proceeds from financing activities in the normal course of business" cover the next 12 months; the last clause carries the weight. Concentration is third: three customers are 70% of revenue. Smaller items: a Canada Revenue Agency dispute over about $28M of GST, not accrued. One older risk is gone: in October, U.S. Customs accepted IREN's protests on a roughly $100M tariff claim on mining hardware.
The Bottom Line
IREN has done the hard part of the pivot: customers have signed, prepaid $2.5 billion and pushed AI Cloud to 88% of revenue. What the quarter shows is that the build is now financed at the margin by 10% equipment loans and by share sales at prices that are gone, while signed commitments run more than twice the cash and credit in hand. Watch three things in the February 10-Q: whether the commitments number falls (using the new cancellation language) or rises, how much of GPU Financing 2.0's $1.5B is drawn by its December 31 deadline, and whether the $4B ARR lands by January 31.
Nobody wrote these numbers down by hand. Every figure on IREN's own business above came out of its SEC filings, read and checked by machine, and the same work runs on any of the companies that file with the SEC, or on a private company that keeps its books in the same format.
Figures on IREN's results, balance sheet, debt and commitments are from its Form 10-Q for the quarter ended September 30, 2026, its fiscal 2026 Form 10-K and its November 5, 2026 earnings release (Form 8-K), retrieved through the RoboSystems SEC Shared Repository. Prices, consensus and peer multiples are attributed and dated where they appear.
Ask the filing yourself
Every figure in this report came from IREN Limited's SEC filings in the RoboSystems SEC Shared Repository. Connect it to Claude or ChatGPT and ask your own questions, starting with this one:
What were IREN's capital commitments at September 30, 2026, and how do they compare with its cash, restricted cash and undrawn debt facilities?